China 220kv 161kv 69kv 33kv Power Transformer Distribution Transformers Power Substation up to 320mva, Find details about China Power Transformer, Transformer from 220kv 161kv 69kv 33kv Power Transformer Distribution Transformers Power Substation up to 320mva
Cooling method | |||||
Winding | Connection | OLTC Position | Voltage | ||
(kV) | Current A | ||||
(ONAN) | Current A | ||||
(ONAF) | |||||
HV | Star | 1 | 207 | 529.9 | 892.5 |
9 | 230 | 176.9 | 803.3 | ||
17 | 253 | 433.6 | 730.2 | ||
LV | auto | 9 | 132 | 831 | 1400 |
Tertiary | Delta | 9 | 20 | 685.5 | 1155 |
7. Vector Group YN a0 d11 | |||||
8. Impedance Voltage in Percent at 75 | |||||
Power MVA | winding | Rated voltage kV | Impedance voltage % | ||
320 | HV/LV | 230/132 | 18 | ||
9. No-load Current: 0.2%: | |||||
10. Sustained Short Circuit Current. | |||||
Winding | Max. Sustained Short-circuit Current. Ka | ||||
HV | 8.5 | ||||
LV | 10.4 | ||||
TV | 19 | ||||
11. Max. Duration of Short-circuits in Seconds(s) | |||||
HV: 3s | |||||
LV: 3 s | |||||
TV: 3s |
1. | Pre sale service |
a. | make technical solution |
b. | send quotation, technical data sheet and drawing |
c. | prepare power transmission plan, testing plan and shipment plan |
2. | In sale service |
a. | supervise the manufacturing schedule totally in accordance with the plan |
b. | send photos to customer during every manufacturing process(hold point) |
c. | inform the customer one week before testing. |
3. | After sale service |
a. | installation and commissioning, training the workers |
b. | quick response within 12 hours any time |
c. | provide 12 months guarantee period normally. |