Hot-Selling Optimize Energy Consumption Powder Coating Production Line for LPG Gas Cylinder, Auto Powder Coating Line*

China Hot-Selling Optimize Energy Consumption Powder Coating Production Line for LPG Gas Cylinder, Auto Powder Coating Line*, Find details about China Paint Booth, Spray Booth from Hot-Selling Optimize Energy Consumption Powder Coating Production Line for LPG Gas Cylinder, Auto Powder Coating Line*

Model NO.
HLT
Cylinder Size
3kg-50kg
Workpiece Weight
<30kg
Braced Chain
Qxt250/50kg Light Common Chain
Machine Capacity
2000PCS/12hours
Linear Speed
1.4m/Min
Rated Input Valtage
220-380V
Heating Source
Nature Gas(LPG)
Oven Working Temperature
180-190ºC
Working Method
Auto + Manual
Trademark
HLT
Transport Package
Standard Seaworthy Package
Specification
all sizes cylinders
Origin
Wuxi, Jiangsu
HS Code
8447902000
Model NO.
HLT
Cylinder Size
3kg-50kg
Workpiece Weight
<30kg
Braced Chain
Qxt250/50kg Light Common Chain
Machine Capacity
2000PCS/12hours
Linear Speed
1.4m/Min
Rated Input Valtage
220-380V
Heating Source
Nature Gas(LPG)
Oven Working Temperature
180-190ºC
Working Method
Auto + Manual
Trademark
HLT
Transport Package
Standard Seaworthy Package
Specification
all sizes cylinders
Origin
Wuxi, Jiangsu
HS Code
8447902000
Hot-Selling Optimize Energy Consumption Powder Coating Production Line For LPG Gas Cylinder, Auto Powder Coating Line
Hot-Selling Optimize Energy Consumption Powder Coating Production Line for LPG Gas Cylinder, Auto Powder Coating Line*
 

 

1. Powder coating line design
NoNameDetails
1Workpiece Gas cylinder
2Workpiece materialMetal
3Max. workpiece sizeΦ300×H570(mm)
4Workpiece weight≤30kg
5Braced chainQXT250/50Kg light common chain
6Machine capacity2000pcs/12hours
7Hanging typeOne cylinder every two pitch, that means one cylinder per 500mm.
8Linear speed2000pcs÷12h÷60min×0.5m/hang=1.4m/min
9Heating sourceNature gas(LPG)
10Location areaSee layout drawing, beam bottom height 8.5 meters
 Hot-Selling Optimize Energy Consumption Powder Coating Production Line for LPG Gas Cylinder, Auto Powder Coating Line*

2. Process flow diagram
This line consists of powder coating chamber, booth, curing bake, suspend conveyor and electric control system.
NoNameTransit timeWorking temperatureOperation
1Loading  RTManual
2Powder coating RTAuto+manual
3baking17-18min180-190ºCHeated air circle
4cooling20min  
5unloading  Manual
 
3. Curing bake
The drying tunnel consists of three parts: drying tunnel. Heating system and exhaust system.
3.1 Drying tunnel
 
NoNameTechnical parameter
1Overall structure Bridge type
2No of tunnels4
3Size of the inner tunnelL14×W3.2×H2.1(m). Leg height 2.5meters
4Thickness of the insulation150mm
5Material of the insulationHigh quality rock wool board
6Unit weight of the insulation100Kg/m3
7Material of the inner plateδ0.8 galvanized steel sheet
8Metarial of the outer plateδ0.8 color sheet
9Structure of inner and outer plateAssembly structure
10Material of the inner angle plateδ1 galvanized steel sheet
11Material of the outer angle plateδ3 hot-rolled sheet with paint
12Supporter material of the tunnelδ3 carbon steel sheet, edgefold with paint
13Outer temperature of the tunnelLower than environment temperature 15ºC
14Inner temperature of the tunnel180ºC
15Drain cracking-offTop of the tunnel
 
3.2. heating system: consists of heating chamber, burner, heated air recycling fan, return airway and temperature control system.
(1)heating room: an access door is on the side of the heating chamber for future repairing.
NoName Technical parameter
1Position and number of heating roomBottom of the bake tunnel, 1 set
2Heating room configuration300000 calories, 1 set
3Inner plate of the heating roomGalvanized steel, δ1
4Outer plate of the heating roomCold-roll steel sheet, δ1.5
5Thickness of the insulation150mm
6Material of the insulationHigh quality rock wool board
7Unit weight of the insulation100Kg/m3
8Material of the inner angle plateδ1 galvanized steel sheet
9Material of the outer angle plateδ3 hot-rolled sheet with paint
10Supporter material of the tunnelδ3 carbon steel sheet, edgefold with paint
11Structure of inner and outer plateAssembly structure
 
(2) burner
1 set, 300000 calories
Gas consumption: 10-15m3/h
Brand: Italian Riello RS34
 
(3)burning tank
Heat exchanger is used to transfer the heat to heating room, then hot-air blower will bring the heat to the tunnel. Adopts direct-fired heating, the burning tank is stainless steel with high temperature filter.
 
(4)Thermal cycling fan: adopts special air-cooled centrifugal fan
NoNameParameter
1Model GCF-630C
2Rotation speed1250r/min
3Air flow volume13500m3/h
4Total pressure900Pα
5Motor power5.5KW
6Fan structureImpeller is in the heating room
7Insulation thickness150mm
9Impeller material16Mn
10No. Of fans1 set
11Fans supplierShanghai Shuyuan or Kewangda
 
(5) Air delivery & returning duct
 
NoNameParameter
1Hot air recyclingInternal recycle, no outer tubes
2Air delivery typeUnder floor air delivery
3Air returning typeUnder floor air returning
4Duct materialGalvanized steelδ1
5No of air regulation plate1 set
6Material of air regulation plateGalvanized steelδ1
(6) Temperature control system
Drying tunnel uses digital temperature controller to adjust the temperature automatically, it can display and control the drying tunnel temperature in real-time.
The temperature measurement uses platinum resistor temperature sensor.
The drying tunnel temperature can be adjusted continuously from normal temperature to 200°C.
 
3.3. Exhaust pipe
The entrance/exit of the drying tunnel on the top equips with exhaust pipe and  butterfly valve, it is used for draining the exhaust gas of the drying tunnel.
The material of the exhaust pipe is δ1mm galvanized sheet.
 Hot-Selling Optimize Energy Consumption Powder Coating Production Line for LPG Gas Cylinder, Auto Powder Coating Line*

4. Hang type conveyor
Hang type conveyor consist of driving device, tension device, variable-frequency governor, chain, straight conveyor, bend conveyor, temperature flexible conveyor, inspection conveyor and lubrication system etc.
Variable -frequency governor uses Mitsubishi. The speed is 1.4 m/min.
The lubrication system uses automatic oil drop device.
Hang type conveyor equips with 1 set driving device, 1 set weight-loaded type tension device, using frequency to adjust speed.
 
NoNameTechnical specification
1Driving device modelQXT-250
2Driving device quantity1 set
3Overload protection for driving deviceAdjustable safety clutch+travel switch
4Driving device power3.0KW
5Tension device typeWeight-loaded type
6Tension device quantity1set
7Turning radius of tension device≥R800(mm)
8Frequency converterMitsubishi 1 set
9Conveyor chain length125m
10Conveyor chain pitch250mm
11Hoisting weight of conveyor chain single point50Kg
12Production speed1.4m/min
13Production speed adjustable methodFrequency control(0.6-2.0m/min)
14Column quantity,materialComplete set, steel section
15Bottom plate quantity,materialComplete set, hot-rolled sheet steel
16Beam quantity,materialComplete set, steel section
17Diagonal bracing quantity,materialComplete set, steel section
18lubrication systemAutomatic oil drop device 1 set
19"C" type jig and rotary rack250 pcs
20Rotary rack1set
 Hot-Selling Optimize Energy Consumption Powder Coating Production Line for LPG Gas Cylinder, Auto Powder Coating Line*

5. Powder coating system
5.1. Technical parameter
Machine typeManual
 
Max. Hang range of the workpiece
 
W310xH570
Conveyor speed
 
About 1.4m/min
 
Type of conveyorSuspend conveyor
 
Coating material
 Polyester powder and epoxy powder
Color2 kinds
Powder supplier
 Local
Type of coating chamber
 Filter type powder coating chamber
Type of powder coating systems
 Corona torch
No of powder coating systems
 6 sets auto, 1 set manual spraying torch
Type of hoister
 Reciprocating hoister
No of hoister1 set
No of the torch on the hoister2 sets on left, 2 sets on top, 2 sets on bottom
Suction capacity of coating chamber11000 m3/h
Required pressure for compressed air
 6 - 8 bar , + 0.1 bar
Remaining water in the compressed air
 Max. 1.3 g/N m3 
Remaining oil in the compressed airMax. 0.1 mg/N m3  
Estimated air consumption for chamber
 120 N m3/h
Power supply220/380 VAC, 50Hz, 3L/N/PE, 3 phase 5 wires
Estimated power consumption for powder coating 
 Approx. 10 KVA
Estimated power consumption for chamber
 15KVA  -- powder coating chamber
Requirement for operation conditionRelative humidity<80%
Ambient temperature< 30ºC
Air speed near the chamber< 0.1 m/sec

6. Package and Delivery
Hot-Selling Optimize Energy Consumption Powder Coating Production Line for LPG Gas Cylinder, Auto Powder Coating Line*

7.Successful Cases
3kg, 6kg, 12kg LPG cylinder powder coating line in Kenya
Hot-Selling Optimize Energy Consumption Powder Coating Production Line for LPG Gas Cylinder, Auto Powder Coating Line*

12kg LPG cylinder powder coating line in Bangaladesh

Hot-Selling Optimize Energy Consumption Powder Coating Production Line for LPG Gas Cylinder, Auto Powder Coating Line*


8. Our Company

Wuxi Longterm Machinery Technologies Co.,Ltd. is an influential manufacturer of coating equipment,environment-protective plating equipments, green environment-protective powder and other specialized coating production.Our company pays attention to product innovation, with 20 invention patents and 119 utility model patents.
Our products are sold to domestic and international famous enterprises:Cheetah car etc., JinGu\Jinfei car parts, Yueling car parts,Electrolux, Siemens, Philip , Atlas,WAM and domestic long march Launch Vehicle, Haier, Hisense,and exported to Russia, Vietnam, India, Syria , Pakistan, Mexico and more than 20 countries, while is the coating supplier for China Business Aircraft Group in 2009.
Hot-Selling Optimize Energy Consumption Powder Coating Production Line for LPG Gas Cylinder, Auto Powder Coating Line*


Patent And Enterprise Certificate.
Wuxi Longterm coating is national hi-tech company, and has been awarded several honorary title by national and provincial government
Hot-Selling Optimize Energy Consumption Powder Coating Production Line for LPG Gas Cylinder, Auto Powder Coating Line*


9. FAQ
Q: What size of LPG cylinder your machine can powder coating?
A: 6kg, 12kg,15kgs and 50kgs LPG cylinder for cooking and other size according customers' requirement.

Q: About the price
A: The price showing on website is not the real because vary item with different price. The final quotation based on two side (customer and manufacturer) confirmed the technology project afterwards.

Q: Production cycle
A: We are a professional manufacturer of providing the powder coating system. Ensure providing a qualified  product and service, we are setting the production cycle is 60 working days. The actually lead time depends on the recent actually production planning.

Q: Service
A:We will offer the whole plant design proposal freely before place order. We are welcome customer visiting the coating line onsite anytime. We will prepare the detailed  technology proposal after get approval between customer and manufacturer. 


Enable us provide the most suitable proposal for you, please tell me following details:
1.Workpiece size/specification,weight and process requirements(Powder coating or painting?)

2.Plant foundatation drawing,including plant height (the height between factory beam to the ground) and loading&unloading position

3.Heating energy: Electric, LPG or LNG?

4.The environmental requirements of your local government

5.Voltage 

6.Daily and annual capacity.