China 1.2t Electric Arc Furnace, Find details about China Electric Arc Furnace, Eaf from 1.2t Electric Arc Furnace
SN | Description | Unit | Data |
1 | Rated capacity | T | 1.2t |
2 | Max. tapping | T | 2t |
3 | Diameter of shell | mm | Φ2000 |
4 | Electrode pitch circle diameter | mm | Φ600 |
5 | Electrode diameter | mm | Φ200 |
6 | Electrode travel stroke | mm | 1100 |
7 | Electrode lifting speed(up/down) | m/min | 4/3 |
8 | Max. steel tapping angle (forward) | 45° | |
9 | Max. slag tapping angle (backward) | 15° | |
10 | Max. roof swivel angle | 80° | |
11 | Roof lifting stroke | mm | 200 |
12 | Transformer capacity with water/oil cooler | kVA | 1250 |
13 | Transformer primary voltage | kV | 10 |
14 | Transformer secondary voltage | V | 210-110 |
15 | Rated secondary current | A | 3400 |
16 | Electrode lifting mode | VVVF | |
17 | Cooling water circulating flow rate | T/h | 25 |
SN | Item | Qty | Remark |
1 | Furnace body | 1 set | |
2 | Tilting mechanism | 1 set | |
3 | Roof ring | 1 set | |
4 | Roof lifting & swivel mechanism | 1 set | |
5 | Conductive arms | 1 set | |
6 | Electrode lifting mechanism | 1 set | |
7 | Cooling water distributer | 1 set | |
8 | Hydraulic power pack | 1 set | Proportional valves and pumps make: Parker |
9 | Short net | 1 set | |
10 | L.V. Power and control panels | 1 set | |
11 | PLC control system & HMI | 1 set | Siemens S7-300 |
12 | 10kV H.V. switchboard | 1 set | China make |
1. | Pre sale service |
a. | make technical solution |
b. | send quotation, technical data sheet and drawing |
c. | prepare power transmission plan, testing plan and shipment plan |
2. | In sale service |
a. | supervise the manufacturing schedule totally in accordance with the plan |
b. | send photos to customer during every manufacturing process(hold point) |
c. | inform the customer one week before testing. |
3. | After sale service |
a. | installation and commissioning, training the workers |
b. | quick response within 12 hours any time |
c. | provide 12 months guarantee period normally. |
1. Q: | What is your delivery time ? |
A: | Depend on the type of transformer. |
2. Q: | What is your payment term? |
A: | 30% advance by T/T , 70% before delivery by T/T or L/C or we can discuss about it. |
3. Q: | What kind of standard you follow? |
A: | IEC, ANSI, CSA, GB, etc |
4. Q: | What kind of supporting documentation you can provide normally |
A: | Quotation, outline drawing, manufacturing plan, quality control plan testing plan, financial report, type test report(KEMA, CESI),reference list, etc |
5. Q: | What is your normal warranty period? |
A: | 12 months after transformer operation. |
6. Q: | Can u do installation and commission in user's site? |
A: | Yes, we can send our installation team to user's country for service. |
7. Q: | Do you have any experience in this kind of transformer? |
A: | Yes, we can provide reference list for check. |